How long does a typical residential painting job take in Ottawa?
- Axcell Painting

- Feb 3
- 2 min read

You want a straight answer.
You also want to know why your neighbor’s “two-day job” turned into two weeks.
Time depends on scope, prep, and dry time.Not the calendar. Not guesswork.
Here’s what actually happens on real homes across Ottawa neighborhoods.
Interior Room Painting (Walls, Ceilings, Trim)
Average time: 1–2 days per room
What controls the clock:
Furniture moving and floor protection
Drywall repairs and sanding
Caulking gaps in trim
Two full coats with proper cut lines
Dry time between coats (winter helps here)
Example:
Bedroom or office → 1 day
Large living room with ceilings and trim → 2 days
If you hear “we’ll be in and out in a few hours,” prep is getting skipped.
Whole Interior Repaint
Average time: 3–6 days
Typical Ottawa detached home (1,800–2,500 sq ft):
Day 1: Protection, prep, repairs
Day 2–4: Ceilings, walls
Day 5–6: Trim, doors, touchups
Why winter is faster:
Low humidity
Faster curing
Windows stay closed so dust stays out
This is why winter is prime time for interior projects.
Kitchen Cabinet Painting (Spray Finish)
Average time: 7–10 days total
This surprises most homeowners.
Because cabinet painting is not “painting in your kitchen.”
Process used by Ottawa Cabinet Painting:
Day 1: Remove doors/drawers, label, transport to spray booth
Day 2–6: Clean, sand, prime, spray multiple coats in a dust-free booth
Day 7: Cure time with hardeners
Day 8–10: Reinstall and final adjustments
Your kitchen stays usable the entire time.
That timeline is about curing, not labour.
Exterior House Painting
Average time: 3–5 days
Depends on:
Height and ladder work
Scraping and sanding peeling areas
Weather windows
Sun exposure by elevation
Small bungalow → 3 daysTwo-storey with trim detail → 5 days
Rain resets the clock. Prep cannot be rushed outdoors.
Trim, Doors, and Detail Work Only
Average time: 2–3 days
This takes longer than people expect.
Why:
Dry time between enamel coats
Sanding between coats for smooth finish
Clean lines where trim meets walls
This is where “crisp lines” come from.
What Slows Projects Down
These add days fast:
Poor prep from previous painters
Dark colors being covered with white
Heavy drywall repairs
Occupied rooms with lots of contents
Rushed crews trying to “save time”
You don’t see these in quotes. You see them in delays.
What Speeds Projects Up
Large, organized crew
Clear rooms before painters arrive
Choosing colors before start day
Doing work in winter months
Hiring a team that does prep first, paint second
That’s how Axcell Painting & Decorating finishes full homes in under a week when timelines matter.
Quick Timeline Cheat Sheet
1 room → 1–2 days
Whole interior → 3–6 days
Cabinets (spray booth) → 7–10 days
Exterior → 3–5 days
Trim & doors only → 2–3 days
If a quote promises faster than this, ask what step is being skipped.
Want a Real Timeline for Your Home?
Every house is different.
You can get a clear plan in under 48 hours.
Call 613-722-1059 or request a quote at www.axcellpainting.com
You’ll know exactly how many days your project needs. And why.